RENOVATION DE LA COUR DES PARKINGS

• LES PROBLEMES:

Etanchéité des circulations

Conservation du lanterneau

Page 3: Cour pk

Etat actuel

Page 4: Cour pk

Etat Actuel

Page 5: Cour pk
Page 6: Cour pk
Page 7: Cour pk
Page 8: Cour pk
Page 9: Cour pk

Corrosion et rupture de ferraillage

Page 10: Cour pk
Page 11: Cour pk
Page 12: Cour pk
Page 13: Cour pk
Page 14: Cour pk

RENOVATIONCOUR DES PARKINGS

• PROBLEME:

• ETANCHEITE DES CIRCULATIONS

• Surface: 125 m2

Page 15: Cour pk
Page 16: Cour pk

Etat actuel

Page 17: Cour pk

RENOVATION COUR DES PARKINGS

• PROBLEME :• CONSERVATION DU LANTERNEAU EXISTANT

VERIFICATION DE LA STRUCTURECALCUL REPORT DES CHARGES

ETUDE DE FAISABILITE

Page 18: Cour pk
Page 19: Cour pk
Page 20: Cour pk
Page 21: Cour pk
Page 22: Cour pk
Page 23: Cour pk
Page 24: Cour pk
Page 25: Cour pk
Page 26: Cour pk
Page 27: Cour pk
Page 28: Cour pk

BUDGET PREVISIONNEL

ETUDE DE FAISABILITE: 10 k€

ETANCHEITE DES CIRCULATIONS50 à 60 k€

(Selon état de la forme de pente existante)

DEMOLITION LANTERNEAUTERRASSE VEGETALISEE

160 à 175 k€(Suivant prise en compte des normes de ventilation)

TOTAL 0PERATION210 à 235 k€

Soit 70 à 78 € par tantième