    NOKIA PLANTA II.

    Parque Industrial Villa Florida.

    Attention:

    Ing. Jesus Romero y/o Alberto Johansen.

    Issue:

    Report the incident that occurred with the detection and alarm system.

    The Friday March 16th 2012 we go to the Nokia building for review of a situation that occurred

    with the detection and alarm system in the server.

    We were informed that while working on some maintenance on the loop alarm system in a given

    area, occurred downloading the server room system

    We proceed to review the history to see if we have any indication which may have been thecause of the activation.

    According to records obtained no evidence of any cause (we refer to some activation by adevice programmed in the discharge area) what had caused the system discharge.It leads us todeduce and according to the activities being carried out it was a mistake in the process of theactivity to be performed,this is when we make a communication breakdown with loop devices,the system send an invalid response problem (INVALID REPLY).

    As a precaution we, when there are discharge zones programmed into alarm panel, we removeor disconnect the solenoids for the following reason: when the loop is connected to this systembegins to communicate with each of the devices which indicate their presence by a pulse

    generated as the communication protocol, in the case of the control modules is a situation thatmust be considered since they generate short pulses in the range of microseconds aresometimes sufficient to energize an device installed in output,therefore always be carried outsuch an activity is recommended to remove or de-energize the solenoid.

    Therefore, due that system does not record any device of the discharge zone that had beenactivated as to cause discharge Inergen system, We think that what happened was when thecontrol module sent the pulse to be recognized by the control panel.

    On the other hand was seen in the history , recurring problems of communication of groundfailures,even, on several occasions have been accessed the programming mode ;this latter if itis not performing by qualified personnel for the programming of this type of equipment, could bea possible cause of an equipment malfunction.

    We recommend making a good review of the system wiring and making some adjustments inprogramming.

    We wish to emphasize that, as SIMARSA a company which was certified last year taught byNOTIFIER ONYX UNIVERSITY; we can give your company the technical assistance required inthis field