Support TG 96

Embed Size (px)

Citation preview

  • 7/27/2019 Support TG 96

    1/26

    SOUTH AUSTRALIAN W

    TECHNICAL G

    Issued by:

    Issue Date:

    GUIDELINCHOR

    BU

    UNREST

    ANCHORAGE

    TER CORPORATION

    IDELINE

    Manager Engineering

    10 May 2007

    T

    ES FOR THE DESIGNAND THRUST BLOCKIED PIPELINES WITH

    AINED FLEXIBLE JOIAND FOR THEOF PIPES ON STEEP

    96

    OFON

    TS

    RADES

  • 7/27/2019 Support TG 96

    2/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    SA Water 2007

    This document is

    be reproduced, c

    express written pe

    The information c

    intended recipient

    These Guidelines

    Water makes no

    information for an

    It is the respons

    application of inf

    Guidelines are fit

    Standards, Acts

    responsibility for

    Guidelines.

    SA Water and its

    reliance on these

    misstatement, mis

    Users should in

    application of info

    The currency of th

    Major Changes Inc

    1. The follow

    96:Section

    of Disadva

    2. Section 6

    3. Section 4.

    changed.

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    copyright and all rights are reserved by SA

    pied or transmitted in any form or by any

    rmission of SA Water.

    ntained in these Guidelines is strictly for th

    in relation to works or projects of SA Water.

    have been prepared for SA Waters own i

    representation as to the quality, accuracy

    other purpose.

    ibility of the users of these Guidelines t

    rmation is appropriate and that any desig

    or SA Waters purposes and comply with all

    and regulations. Users of these Guide

    interpretation and use of the information

    officers accept no liability for any loss or

    Guidelines whether caused by error, omi

    interpretation or negligence of SA Water.

    ependently verify the accuracy, fitness

    mation contained in these Guidelines.

    ese Guidelines should be checked prior to u

    rporated In the May 2007 E

    ing lists the major changes to the May 2

    2.5 - Restrained Joints, additional dot poin

    ntages/Issue in this section.

    Corrosion Requirements, changes made to

    2, 4.3, 4.4 & 4.5 numeric value in the

    07

    d on printing

    Page

    2 of 26

    ater. No part may

    means without the

    private use of the

    ternal use and SA

    or suitability of the

    o ensure that the

    s based on these

    relevant Australian

    lines accept sole

    contained in these

    amage caused by

    sion, misdirection,

    for purpose and

    se.

    ition

    007 edition of TG

    , plus the inclusion

    paragraph 6.2.

    formula has been

  • 7/27/2019 Support TG 96

    3/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Contents

    SA WATER 2007 ...............

    MAJOR CHANGES INCORP

    SECTION 1: SCOPE ............

    SECTION 2: DEFINITIONS ..

    2.1 UNRESTRAINED FLE2.2 PIPE SPECIAL ...........2.3 ANCHOR BLOCK .......2.4 THRUST BLOCK ........2.5 RESTRAINED JOINTSSECTION 3: GEOTECHNIC

    3.1 GEOTECHNICAL DES3.2 GEOTECHNICAL ASS3.3 CONSTRAINTS ON A3.4 ALLOWABLE HORIZOSECTION 4: DESIGN OF A

    4.1 DESIGN HEAD ...........4.2 THRUST BLOCKS AT4.3 THRUST BLOCKS AT4.4 ANCHOR BLOCKS AT4.5 ANCHOR BLOCKS AT4.6 PREPARATION OF DSECTION 5: THRUST COLL

    5.1 THRUST COLLARS A5.2 PUDDLE FLANGES ASECTION 6: CORROSION

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    .....................................................................

    ORATED IN THE MAY 2007 EDITION ........

    .....................................................................

    .....................................................................

    IBLE JOINT ................................................

    .....................................................................

    .....................................................................

    .....................................................................

    ....................................................................

    L .................................................................

    IGN PRINCIPLES ........................................

    ESSMENT OF EACH LOCATION ................

    CHOR AND THRUST BLOCK LOCATION .

    NTAL BEARING PRESSURES ....................

    CHORS & THRUST BLOCKS ....................

    .....................................................................

    BENDS ........................................................

    TEES AND DEAD ENDS .............................

    TAPERS AND REDUCERS ........................

    VALVES AND TEMPORARY DEAD ENDS

    AWINGS FOR ANCHORS AND THRUST

    ARS AND PUDDLE FLANGES ...................

    ANCHORS ON MSCL PIPELINES ............

    ANCHORS ON DICL PIPELINES ..............

    EQUIREMENTS ..........................................

    07

    d on printing

    Page

    3 of 26

    ........................... 2

    ........................... 2

    ........................... 5

    ........................... 5

    ........................... 5

    ........................... 6

    ........................... 6

    ........................... 6

    ........................... 7

    ........................... 8

    ........................... 9

    ........................... 9

    ..........................10

    ..........................10

    ..........................13

    ..........................13

    ..........................13

    ..........................14

    ..........................15

    ..........................16LOCKS .............17..........................18..........................18..........................18..........................18

  • 7/27/2019 Support TG 96

    4/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    6.1 CORROSION REQUIR6.2 CORROSION REQUIRSECTION 7: PIPE ANCHOR

    7.1 PIPE ANCHORAGE O7.2 PIPE ANCHORAGE O7.3 PIPE ANCHORAGE OAPPENDIX A: DRAWINGS..

    Tables & Figures

    Table 3.1 - Allowable Horizon

    Figure 7.1 - Pipe Anchorage

    Figure 7.2 Pipe Anchorage on

    Figure 7.3 - Pipe Anchorage

    Referenced Docum

    TS 4b

    TS 81

    Standard Drawing 75 2A

    Drawing 98-0021-01

    Transport SA specification

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    EMENTS ON MSCL PIPE SPECIALS .........

    EMENTS ON DICL PUDDLE FLANGES .....

    AGE ON STEEP GRADE ............................

    N GRADES LESS THAN 20% ......................

    N GRADES BETWEEN 20% AND 25% .......

    N GRADES STEEPER THAN 25% ..............

    .....................................................................

    al Bearing Pressures for Anchors and Thrus

    n Grades between 20% and 25%. ...............

    Grades Steeper than 25%. .........................

    n Grades Steeper than 25%. .......................

    ents

    A10-7

    07

    d on printing

    Page

    4 of 26

    ..........................18

    ..........................19

    ..........................19

    ..........................19

    ..........................19

    ..........................21

    ..........................24

    t Blocks. ............11

    ..........................20

    ..........................22

    ..........................23

  • 7/27/2019 Support TG 96

    5/26

  • 7/27/2019 Support TG 96

    6/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    angular deflection

    gentle curve.

    2.2 PIPE SPECIAL

    A pipe special is

    of anchor and thr

    tee, stop end, or a

    On a pipeline with

    be restrained usin

    2.3 ANCHOR BLOC

    A conventional an

    a straight piece

    longitudinal move

    The longitudinal t

    puddle flange cla

    to the pipe (for M

    The anchor block

    thrust into undistu

    Anchor blocks will

    possible to use th

    2.4 THRUST BLOCK

    A thrust block i

    than around, the p

    A conventional th

    block designed to

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    at each joint so that the pipeline can be

    any specially fabricated or precast piece of

    ust block design, a pipe special will usuall

    flanged length of pipe bolted to a valve.

    unrestrained flexible joints, a pipe special w

    g an anchor or a thrust block.

    chor block is a reinforced concrete block w

    f pipe, and which is designed to restrai

    ent. Refer to Drawing 98-0021-01.

    hrust from the pipe is transferred into the

    ped onto the pipe (for DICL pipes) or via a

    CL pipes).

    is cast into slots cut into the trench wall s

    rbed native soil.

    normally only be used at in-line valves or ta

    much simpler thrust block.

    a simple unreinforced block of concrete

    ipe special.

    rust block at a horizontal bend or tee w

    transfer the thrust from the pipe into the un

    07

    d on printing

    Page

    6 of 26

    made to follow a

    pipe. In the context

    be a bend, taper,

    ill normally need to

    hich is cast around

    the pipe against

    anchor block via a

    hrust collar welded

    as to transfer the

    ers, where it is not

    ast against, rather

    uld be a concrete

    isturbed native soil

  • 7/27/2019 Support TG 96

    7/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    in the trench wall.

    A conventional thr

    to that for a horiz

    wall.

    A conventional thr

    concrete attached

    Note that an anch

    branch of a tee c

    legs of a bend

    because of the e

    blocks where con

    conflict with other

    cross trenches.

    2.5 RESTRAINED JO

    A restrained join

    restrained again

    (proprietary) meta

    system used on T

    RRJ Ductile Iron

    for pipes in the si

    do not work in co

    Restrained joints

    anchorage syste

    they can be used i

    Some of the ben

    are:

    No concrete

    providing co

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    ust block at a vertical bend (downward thru

    ontal bend, but would bear on the trench fl

    ust block at a vertical bend (upward thrust)

    to the pipe with sufficient weight to counterb

    or block can be used instead of a thrust bloc

    uld be extended and an anchor placed on

    ould be extended and an anchor placed

    tra cost, anchor blocks would only be use

    itions at the bend precluded the use of a thr

    services, weak natural soils, disturbed soils,

    INTS

    t is a usually conventional flexible rubbe

    t pullout and angular deflection by th

    l claw device in the rubber ring. An exam

    yton Ductile Iron pipes. Restrained joints ar

    ement (mortar) Lined (DICL) pipes and fitti

    e range of 100 to 300 mm nominal diamete

    pression.

    can be used either to create a comple

    (as an alternative to concrete anchors

    in association with concrete anchors or thrus

    fits of restrained joint anchorage systems

    is required. This is convenient in areas w

    ncrete is difficult.

    07

    d on printing

    Page

    7 of 26

    st) would be similar

    oor rather than the

    is simply a block of

    alance the thrust.

    k. For example, the

    he branch, or both

    on each leg. But

    d instead of thrust

    ust block there - eg

    or the presence of

    r ring joint that is

    e inclusion of a

    le is the Tyton-Lok

    e available only for

    ings, and then only

    r. Restrained joints

    e restrained joint

    r thrust blocks) or

    t blocks.

    on DICL pipelines

    ere the logistics of

  • 7/27/2019 Support TG 96

    8/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    They occup

    space is at

    interference

    The pipeline

    curing time

    convenient

    A complet

    conventiona

    satisfactory

    A short r

    conventiona

    example w

    there is go

    services wo

    Manufactur

    joints to pro

    Disadvantages/Is

    Cut-ins diffic

    Must be ma

    Locking gas

    Incompatibili

    Restrained joint

    manufacturers, bu

    to follow conventi

    Because of this, a

    complete restrain

    usually come with

    design be request

    Section 3: Geotec

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    no space outside of the pipe trench. This i

    a premium in congested service corridor

    by other utilities can be anticipated.

    can be pressure tested and put into servic

    is required for concrete anchors or thr

    hen the commissioning of the pipeline is ur

    e system of restrained joints can be

    l concrete anchors or thrust blocks w

    ground within a reasonable distance.

    n of restrained joints can be used i

    l concrete anchors or thrust blocks. This

    ere the ground at the desired location is

    d ground a short distance away, or wher

    ld otherwise be in the thrust zone of an anc

    rs can specify a minimum length of buried

    ide restraint for a tee or bend etc.

    ues

    ult

    ked as restrained to prevent incorrect repair

    ket may only be used in pipe recommende

    ity problems.

    anchorage system design software is av

    t the design models used in that software do

    nal geotechnical or structural engineering p

    nd because most manufacturers offer a fre

    d joint anchorage systems, and also bec

    a warranty, it is recommended that in gener

    ed and adopted.

    nical

    07

    d on printing

    Page

    8 of 26

    convenient where

    s, or where future

    e immediately no

    st blocks. This is

    ent.

    used instead of

    here there is no

    association with

    ight be useful for

    unsatisfactory but

    other trenches or

    hor or thrust block.

    ipe with restrained

    procedure.

    d by manufacturer.

    ailable from some

    not always appear

    inciples rigorously.

    design service for

    use such designs

    al a manufacturers

  • 7/27/2019 Support TG 96

    9/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    3.1 GEOTECHNICAL

    An anchor or thru

    ONLY into the un

    the pipe embedm

    main reasons for t

    (1) It is genera

    material) su

    any beddin

    can easily

    movement.)

    (2) It is possible

    pressure tes

    no surcharg

    (3) The natural

    the embed

    anyway.

    The designer sho

    thrust on a valve

    therefore specify

    undisturbed nativ

    3.2 GEOTECHNICAL

    Soil conditions, p

    blocks are usuallalmost any road c

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    DESIGN PRINCIPLES

    st block must be designed to transfer the t

    disturbed native soil in the trench wall. On

    ent be relied upon to resist any of the thru

    his:

    lly impossible to compact embedment mat

    ficiently densely against an anchor or thrus

    -in movement. (Trials have shown that be

    e 5 mm or so, which may be half of th

    that the trench fill material will not have be

    t is carried out. If so, the pipe embedment

    load on it and therefore could not resist an

    material is likely to have a much higher stiff

    ent material, and will therefore attract

    ld also be aware that in most pipe network

    etc could come from either direction. Th

    that BOTH faces of an anchor block must

    soil.

    ASSESSMENT OF EACH LOCATION

    articularly at the shallow depths at which

    set, can vary enormously over short distautting or trench wall will reveal.

    07

    d on printing

    Page

    9 of 26

    rust from the pipe

    no account should

    st. There are three

    erial (or any other

    t block to eliminate

    ding-in movement

    e total permissible

    n placed when the

    aterial would have

    horizontal force.

    ness modulus than

    ost of the thrust

    s it is likely that the

    e designer should

    be poured against

    nchors and thrust

    ces, as a study of

  • 7/27/2019 Support TG 96

    10/26

  • 7/27/2019 Support TG 96

    11/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    ultimate horizont

    characteristics w

    characteristics of

    a clay or a sandy

    The assessment

    geotechnical inve

    experience. How

    thrusts are not la

    reasonable to us

    values for allowab

    identification tests

    given in Table 1.

    Note that for larg

    value is likely to r

    prove more econo

    It is clear from th

    ground conditions

    any reasonably s

    scope of these g

    situations, but me

    (a) Using restra

    (b) Pre-loading

    direction).

    (c) Using piles

    (d) Using a w

    conventiona

    Table 3.1 - Allowable Ho

    Trench Wall Material

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    l bearing capacity at failure, but by

    ll below the failure stress. Note that

    soil are governed not so much by the soil t

    oil) but by its density (if a sand) or its consis

    f the allowable horizontal bearing pressur

    stigation at the exact location and consid

    ver, where ground conditions are reason

    rge (eg pipe diameter is less than 300 m

    e simple field identification tests, and to

    le horizontal bearing pressures. Examples

    and conservative allowable horizontal bea

    er pipes (above 300 mm diameter) adopt

    sult in a very large anchor or thrust block,

    mical to investigate the ground conditions at

    e foregoing discussion that there will be si

    are so poor that the allowable movement

    ized conventionalanchor or thrust block.

    idelines to detail other options available to

    tion will be made of a few which could be c

    ined joint anchorage systems (eg Tyton-Loc

    an anchor or thrust block using jacks (ca

    r piers.

    lded special to transfer the thrust to a

    l anchor or thrust block can be used.

    rizontal Bearing Pressures for Anchors and

    Field Identification Test

    (1)

    07

    d on printing

    Page

    11 of 26

    its load-deflection

    he load-deflection

    pe (ie whether it is

    tency (if a clay).

    clearly requires a

    rable geotechnical

    bly good, and the

    ), then it may be

    dopt conservative

    f some simple field

    ring pressures are

    ing a conservative

    nd so it is likely to

    each location.

    tuations where the

    ill be exceeded by

    It is not within the

    designers in such

    nsidered, namely:

    ).

    only work in one

    location where a

    hrust Blocks.

    Allowable

    Horizontal

    Bearing

    Pressure (2)

  • 7/27/2019 Support TG 96

    12/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    CLAYSVery Soft C

    Soft Cla

    Firm Cla

    Stiff Cla

    Very Stiff C

    Hard Cla

    SANDSLoose Clean

    Medium-Dens

    Sand

    Dense Clean

    Gravel

    ROCK

    Broken o

    Decomposed

    Sound Ro

    UNCOMPACTED FIL

    DOMESTIC REFUSE

    (1) All field identification tests

    trench wall by an enginee

    ensure that the soil in the

    soil in the trench floor is v

    and time allowed for the w

    (2) For anchors and thrust bl

    with SA Water reticulation

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    lay Easily penetrated 40 mm with fist

    Easily penetrated 40 mm with thumb

    Moderate effort needed to penetrate

    30 mm with thumb

    Readily indented with thumb but penetrate

    only with great effort

    lay Readily indented by thumbnail

    y Indented with difficulty by thumbnail

    SandTakes footprint more than

    10 mm deep

    Clean Takes footprint 3 mm to

    10 mm deep

    and or Takes footprint less than

    3 mm deep

    r

    Rock

    Can be dug with pick. Hammer blow thuds

    Joints spaced less than 300 mm apart.

    ck Too hard to dig with pick. Hammer blowrings. Joints more than 300 mm apart.

    Visual inspection of the materials and/or a

    knowledge of the history of the site.

    must be done on a freshly exposed, damp, han

    r / technical officer competent in such work. C

    est area was not compacted or loosened during

    ry dry at the time the trench is opened, the test

    ater to be absorbed by the soil before trimming a

    cks with the centre of thrust about 1 m below t

    systems where normal cover to the pipe is 750

    07

    d on printing

    Page

    12 of 26

    (3)

    (3)

    (3)

    50 kPa

    100 kPa

    200 kPa

    (3)

    50 kPa

    100 kPa

    .100 kPa

    200 kPa

    (3)

    -trimmed area of the

    re must be taken to

    the excavation. If the

    area must be flooded

    nd testing.

    he surface as occurs

    m.

  • 7/27/2019 Support TG 96

    13/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    (3) Standard values cannot b

    Section 4: Design

    4.1 DESIGN HEAD

    The design head f

    For SA Water reti

    For water supply

    etc, the test press

    pressure will gen

    multiplied by an a

    4.2 THRUST BLOCK

    Thrust blocks a

    unrestrained flexi

    thrust. It is assu

    native soil or ro

    compacted fill).

    The thrust block s

    when located in a

    i) For pipeline

    of 1.6 MPa (

    Constructio

    thrust block

    laid at the m

    ii) For pipeline

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    used - specialist geotechnical investigation and

    f Anchors & Thrust Blocks

    or anchor and thrust blocks will generally be

    ulation systems the test pressure is 1.6 MP

    runk mains, sewer rising mains, irrigation

    ure will be determined by the designer of th

    erally be the operating pressure (includin

    propriate factor of safety.

    AT BENDS

    horizontal and vertical bends on buri

    le joints are designed to resist the total

    ed that the block transmits all of the thru

    ck only (ie not into the pipe embedme

    hould not protrude beyond the space alloca

    road reserve.

    100 to 300 mm in diameter, with a test pre

    160 m head), thrust blocks as shown on th

    Manual Drawings may be used. Note t

    in these drawings is determined on the ba

    inimum cover.

    with test pressures exceeding 1.6 MPa, a

    07

    d on printing

    Page

    13 of 26

    design required.

    the test pressure.

    (160 m head).

    ater supply mains,

    e pipeline. The test

    surge allowance)

    ed pipelines with

    resultant hydraulic

    t into the adjacent

    t material or any

    ion for the pipeline

    ssure not in excess

    appropriate Water

    at the size of the

    sis that the pipe is

    d all pipelines 375

  • 7/27/2019 Support TG 96

    14/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    mm in diam

    the resultant

    where:

    Note that th

    back bend

    thrust block

    between the

    4.3 THRUST BLOCK

    Thrust blocks at

    flexible joints are

    the thrust block tr

    (ie not into the pip

    The thrust block s

    when located in a

    i) For pipeline

    of 1.6 MPa (

    Constructio

    thrust block

    laid at mini

    ii) For pipeline

    mm in diam

    the thrust at

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    eter or greater, the following formula may b

    thrust at a bend:

    T = 1.54 x 10-5 x h x d2 x sin ( / 2)

    T = resultant thrust in kN

    h = effective head in metres

    d = outside diameter of pipe (mm)

    = deflection angle of bend in degrees

    resultant thrust bisects the angle of the b

    ay need to be considered as two separate

    s, one at each end) to avoid bending st

    ends of the lobster-back.

    AT TEES AND DEAD ENDS

    tees and dead ends on buried pipelines

    designed to resist the total hydraulic thrust.

    nsmits all of the thrust into the adjacent nati

    e embedment material or any compacted fill

    hould not protrude beyond the space alloca

    road reserve.

    100 to 300 mm in diameter, with a test pre

    160 m head), thrust blocks as shown on th

    Manual Drawings may be used. Note t

    in these drawings is determined on the b

    um cover and with the minimum allowable t

    with test pressures exceeding 1.6 MPa, a

    ter and greater, the following formula may

    a tee or dead end:

    07

    d on printing

    Page

    14 of 26

    e used to calculate

    nd. A long lobster-

    bends (ie with two

    esses in the pipe

    with unrestrained

    It is assumed that

    ive soil or rock only

    .

    ion for the pipeline

    ssure not in excess

    appropriate Water

    at the size of the

    sis that the pipe is

    ench width.

    d all pipelines 375

    e used to calculate

  • 7/27/2019 Support TG 96

    15/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    where:

    Note that th

    axially along

    4.4 ANCHOR BLOC

    Anchor blocks at

    flexible joints are

    the thrust is trans

    flange (DICL) and

    only (ie never into

    The preferred de

    Anchor Blocks - S

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    T = 0.77 x 10-5 x h x d2

    T = resultant thrust in kN

    h = effective head in metres

    d = outside diameter of pipe (mm)

    e thrust acts axially along the line of the b

    the pipe at a dead end.

    S AT TAPERS AND REDUCERS

    tapers and reducers on buried pipelines

    designed to resist the total hydraulic thrust.

    mitted to the anchor block via a thrust ring

    then from the anchor block into the adjacen

    the pipe embedment material or any compa

    sign model is indicated on Drawing 98-0

    ructural Design Requirements.

    07

    d on printing

    Page

    15 of 26

    anch at a tee, and

    with unrestrained

    It is assumed that

    (MSCL) or puddle

    t native soil or rock

    cted fill).

    021-01 - Concrete

  • 7/27/2019 Support TG 96

    16/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    The anchor bloc

    pipeline when loc

    i) For tapers

    mm, and wi

    anchor blo

    Drawings m

    drawings is

    ii) For pipeline

    reducers wi

    formula ma

    where:

    Note that th

    the larger

    (friction forc

    The anchor

    the taper or

    4.5 ANCHOR BLOC

    Anchor blocks atunrestrained flexi

    transmitted to the

    the anchor block

    material or any

    Drawing 98-0021-

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    should not protrude beyond the space

    ted in a road reserve.

    nd reducers with the larger diameter bet

    h a test pressure not in excess of 1.6 MPa

    ks shown on the appropriate Water C

    ay be used. Note that the size of the anch

    etermined on the basis that the main is laid

    s with test pressures exceeding 1.6 MPa,

    th the larger diameter greater than 375

    be used to calculate the thrust:

    T = 0.77 x 10-5 x h x (D2- d2)

    T = resultant thrust in kN

    h = effective head in metres

    D = outside diameter of larger pipe (m

    d = outside diameter of smaller pipe (m

    e thrust always acts axially along the pipe i

    iameter to the smaller irrespective of th

    s are neglected).

    is usually located on the larger diameter pa

    reducer.

    S AT VALVES AND TEMPORARY DEAD

    valves and temporary dead ends on bule joints are designed by assuming that

    anchor block via a thrust ring or puddle fla

    into native soil or rock. (Ie never into th

    ompacted fill.) The preferred design mo

    01.

    07

    d on printing

    Page

    16 of 26

    allocation for the

    een 100 and 375

    (160 m head), the

    nstruction Manual

    or blocks on these

    at minimum cover.

    and all tapers and

    mm, the following

    )

    m)

    the direction from

    direction of flow

    allel-wall section of

    NDS

    ried pipelines withthe total thrust is

    nge, and then from

    pipe embedment

    el is indicated on

  • 7/27/2019 Support TG 96

    17/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Note that the anc

    the pipeline when

    For pipes betwe

    pressure not in ex

    Water Constructi

    anchor blocks on

    is laid at minimum

    For pipelines wit

    diameter greater

    the thrust at valve

    where:

    Note that the thru

    act in both directio

    4.6 PREPARATION

    To avoid confusio

    or thrust block.

    the drawings. Th

    reinforcement det

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    hor block should not protrude beyond the

    located in a road reserve.

    n 100 mm and 375 mm nominal diamet

    cess of 1.6 MPa (160 m head), the anchor b

    n Manual Drawings may be used. Note t

    these drawings is determined on the assu

    cover.

    test pressures exceeding 1.6 MPa, an

    han 375 mm, the following formula may b

    and temporary dead ends:

    T = 0.77 x 10-5 x h x D2

    T = resultant thrust in kN

    h = effective head in metres

    D = outside diameter of the pipe (mm)

    t acts axially along the pipe, and should be

    ns, even for a valve at a temporary dead en

    F DRAWINGS FOR ANCHORS AND THR

    n on site, a single drawing should be prepa

    here reinforcement is present, its layout s

    use of a typical layout drawing with t

    ils being given in an accompanying table is

    07

    d on printing

    Page

    17 of 26

    pace allocation for

    r, and with a test

    locks shown on the

    at the size of the

    ption that the pipe

    all pipes with a

    used to calculate

    considered likely to

    .

    ST BLOCKS

    ed for each anchor

    ould be shown on

    e dimensions and

    discouraged.

  • 7/27/2019 Support TG 96

    18/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Section 5: Thrust

    5.1 THRUST COLLA

    On MSCL pipelin

    anchor block via

    Design details ar

    for MSCL Pipeline

    5.2 PUDDLE FLANG

    On DICL pipeline

    anchor block via c

    A groove is pre-

    pipe special is u

    groove and puddl

    Section 6: Corrosi

    6.1 CORROSION RE

    Anchor Blocks

    specials at anch

    sacrificial corrosi

    Drawing 75 2A.

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    ollars and Puddle Flanges

    S AT ANCHORS ON MSCL PIPELINES

    s the longitudinal thrust in the pipe wall is

    elded-on thrust collars.

    given on Standard Drawing 75 2A - Stan

    s (appended).

    S AT ANCHORS ON DICL PIPELINES

    the longitudinal thrust in the pipe wall is

    lamp-on pre-cast puddle flanges.

    illed into the wall of the pipe to locate the

    ually supplied by the manufacturer comp

    flange.

    n Requirements

    UIREMENTS ON MSCL PIPE SPECIALS

    n MSCL Pipe Specials: Standard thrus

    r blocks extend beyond the block so tha

    n collars. No additional corrosion collar i

    07

    d on printing

    Page

    18 of 26

    ransferred into the

    ard Thrust Collars

    ransferred into the

    puddle flange. The

    lete with its milled

    collars on MSCL

    t they also act as

    necessary. Refer

  • 7/27/2019 Support TG 96

    19/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Thrust Blocks o

    SintaKote, or are

    the coating or wra

    proposed, a corro

    the contact area o

    6.2 CORROSION RE

    Anchor Blocks

    poured directly ar

    required beneath

    up to the block a

    and sleeving.

    Thrust Blocks o

    sleeved DICL fitti

    be sleeved with P

    Section 7: Pipe An

    7.1 PIPE ANCHORA

    No special ancho

    than 20%. Normal

    in the Water Supp

    7.2 PIPE ANCHORA

    At grades steepe

    place and proper

    component of the

    embedment sand

    percolating grou

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    MSCL Pipe Specials: Where MSCL speci

    wrapped to TS81, the thrust block may be

    pping. In aggressive ground, or where wrap

    sion plate or saddle a minimum of 10 mm th

    f the thrust block and extending 150 mm be

    UIREMENTS ON DICL PUDDLE FLANGE

    n DICL Pipes with Puddle Flanges: T

    ound the DICL pipe puddle flange. No wra

    the concrete. Normal pipe sleeving and wr

    nd denso petrolatum tape used to seal bet

    DICL Fittings: The thrust block is poured

    g. Note, all fusion bonded coated fittings at

    .

    chorage on Steep Grade

    E ON GRADES LESS THAN 20%

    age or laying precautions are required whe

    l embedment in TS4b sand, placed and co

    ly Construction Manual, is sufficient in these

    E ON GRADES BETWEEN 20% AND 25

    r than 20% it becomes increasingly more

    ly compact sand in the embedment zone.

    pipe weight begins to become significant, a

    to creep downhill increases particularly

    dwater. Therefore on grades between

    07

    d on printing

    Page

    19 of 26

    ls are protected by

    ast directly against

    ping to TS81 is not

    ick is required over

    ond it all around.

    S

    e anchor block is

    ping or sleeving is

    apping is extended

    ween the concrete

    directly against the

    thrust blocks shall

    e the grade is less

    pacted as detailed

    situations.

    difficult to handle,

    Also the downhill

    nd the tendency of

    in the presence of

    20% and 25%:

  • 7/27/2019 Support TG 96

    20/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Lay the pip

    uphill.

    Embed the

    SA10-7. (M

    sleeving.)

    Anchor eac

    each socket

    Provide tw

    groundwate

    Cover the

    geotextile or

    Key the bul

    mm each si

    Figure 7.1 - Pip

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    s from the bottom of the hill to the top with

    pipes in 10-7 mm screenings to Transpo

    VC and OPVC pipe only, not UPVC, and

    pipe length with an unreinforced concret

    .

    75 mm diameter holes through each

    to drain down the embedment.

    pstream end of each drain hole with a p

    similar.

    heads into the trench walls 75 mm each sid

    e if in soil.

    e Anchorage on Grades between 20% and

    07

    d on printing

    Page

    20 of 26

    the sockets facing

    rt SA specification

    with care on DICL

    e bulkhead behind

    bulkhead to allow

    atch of non-woven

    e if in rock and 150

    5%.

  • 7/27/2019 Support TG 96

    21/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    7.3 PIPE ANCHORA

    At grades steeper

    even screenings i

    pipe weight beco

    to creep downhill.

    Lay the pip

    uphill.

    Embed the

    workable en

    sprayed con

    Place sand

    flexibility of

    concrete).

    If using pou

    be poured i

    becoming b

    prevent flot

    sprayed con

    Note that th

    more than a

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    E ON GRADES STEEPER THAN 25%

    than 25% it becomes increasingly difficult t

    in the embedment zone. Also the downhill

    es very significant, and ultimately even sc

    Therefore on grades steeper than 25%:

    s from the bottom of the hill to the top with

    full length of each pipe barrel in low-stren

    ough to be pushed under the pipe without

    crete.

    ags around each flexible joint in the pipeli

    the joints (this will also assist with the

    red concrete for the embedment, consider

    n layers to cope with the slope and/or t

    oyant, and that it might also be necessary t

    tion. (Neither the slope nor buoyancy sh

    crete is used.)

    e natural roughness of the trench floor an

    dequate shear interlock with the concrete.

    07

    d on printing

    Page

    21 of 26

    o handle and place

    component of the

    reenings can begin

    the sockets facing

    th concrete that is

    displacing it, or in

    ne to maintain the

    ontainment of the

    hat it may need to

    prevent the pipe

    ballast the pipe to

    uld be an issue if

    walls will provide

  • 7/27/2019 Support TG 96

    22/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Figure 7.2

    Overview of a pipeline on a grade

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    ipe Anchorage on Grades Steeper than 25

    teeper than 25%. Sandbags placed around

    07

    d on printing

    Page

    22 of 26

    .

    ach flexible joint.

  • 7/27/2019 Support TG 96

    23/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Spray concrete embedment b

    Note it flowing under th

    Figure 7.3 -

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    eing applied.

    pipe.A view of the finished spray c

    ipe Anchorage on Grades Steeper than 25

    07

    d on printing

    Page

    23 of 26

    oncrete embedment.

    .

  • 7/27/2019 Support TG 96

    24/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    Appendix A: Drawings

    07

    d on printing

    Page

    24 of 26

  • 7/27/2019 Support TG 96

    25/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    07

    d on printing

    Page

    25 of 26

  • 7/27/2019 Support TG 96

    26/26

    PLANNING &INFRASTRUCTURE

    TG96 -

    Issued

    Design of Pipe Anchorages.docx

    y: Manager Engineering

    10 May 20

    Uncontroll

    07

    d on printing

    Page

    26 of 26