45
LA METHODOLOGIE PMI, basée sur le PMBoK 4 ème Edition. LES 42 PROCESSUS Conception et réalisation: Elysée NGONO MANGA,PMP PMI MemberID : 2083029 Toute reproduction à des fins commerciales est interdite. ElyMad © 2011

PMP Exam - The 42 pmp-processes - 4th Edition

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: PMP Exam - The 42 pmp-processes - 4th Edition

LA METHODOLOGIE PMI, basée sur le PMBoK 4ème Edition.

LES 42 PROCESSUS

Conception et réalisation: Elysée NGONO MANGA,PMPPMI MemberID : 2083029

Toute reproduction à des fins commerciales est interdite.

ElyMad © 2011

Page 2: PMP Exam - The 42 pmp-processes - 4th Edition

2

INITIATING PROCESS GROUP (1/2)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

1 PROJECT CHARTER INTEGRATION La charte du projet

INPUTS TOOLS&TECHNIQUES OUTPUTS/LIVRABLES

oContracts (if exist)

oProject Statement of work (SOW)

o Actifs Organisationnels

o Facteurs Envir

Selecting and Prioritizing Projects Using project Selection MethodsPMOExpert JudgementBenchMarking PMIS

Project Mgnt METHODOLOGY

La charte du projet

By ElyMad © 2011

Page 3: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 3

INITIATING PROCESS GROUP (2/2)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

2 IDENTIFY STAKEHOLDERS COMMUNICATIONS MANAGEMENT

Stakeholder Register

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Project Charter

oActifs Organisationels

o Facteurs Envir

o Contracts (if it’s exist)

STAKEHOLDERS ANALYSIS

SKILLS

PMO

BUREAUX D’EXPERTS

POWER/INTEREST GRID

SILENCE MODELS

Stakeholder Register

La stratégie de Management des Parties Prenantes

Page 4: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 4

PLANNING PROCESS GROUP (1/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

3 DEVELOP PROJECT MANAGEMENT PLAN

INTEGRATION The Project Management Plan

INPUTS TOOLS&TECHNIQUES OUTPUTS/LIVRABLES

o Project Charter

oLes différents Outputs des planning processes

oEnterprise Environmental FactorsoOrganizational Process Asset

PMO

Expert JudgmentLe plan de management du projet / Le Plan Projet/The Project Management Plan

Page 5: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 5

PLANNING PROCESS GROUP (2/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

4 COLLECT REQUIREMENTS SCOPE MANAGEMENT La Documentation des Exigences

INPUTS TOOLS&TECHNIQUES OUTPUTS

o Charte du projeto Stakeholder Register

Les Interviews or Experts interviewingFocus Group/Groupe de Consultation (avec modérateur) Facilated Workshop (JAD or Design, QFD) / ateliers dirigésGroup creativity techniquesTechniques de prises de Décision de Groupe/Group decisions making techniquesQuestionnaires et enquêtesObservationsPrototypesLes Maquettes

Requirement documentation

Plan de management des exigences

Matrice de traçablité des exigences

Page 6: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 6

PLANNING PROCESS GROUP (3/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

5 DEFINE SCOPE SCOPE MANAGEMENT The Scope Statement

INPUTS TOOLS&TECHNIQUES OUTPUTS

o Project Charter

o Requirement documentation

o Actifs organisationnels

EXPERT JUDGMENT

Analyse du produit/ PRODUCT ANALYSIS

FACILITATED WORKSHOP

Identifier les Alternatives / ALTERNATIVE INDENTIFICATION

Project Scope Statement

Mise à jour des documents du projet

Page 7: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 7

PLANNING PROCESS GROUP (4/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

6 CREATE WBS SCOPE MANAGEMENT WBS

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Project Scope Statement

o Requirements Documentation

o Actifs Organisationnels

DECOMPOSITION Le Work Breakdown Structure (WBS)

Le Dico du WBS

Le Scope BaseLine (Scope Statement + WBS + WBS DICO)

Document updates

Page 8: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 8

PLANNING PROCESS GROUP (5/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

7 DEFINE ACTIVITIES TIME MANAGEMENT Activity List

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Scope Baseline

o Facteurs Envir

o Actifs Organisationnels

DÉCOMPOSITION

Rolling Wave Planning

Expert Judgment

Templates / Modèles

Activity List

Activity Attributes

Milestone List/liste des jalons

Page 9: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 9

PLANNING PROCESS GROUP (6/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

8 SEQUENCE ACTIVITIES TIME MANAGEMENT Network diagram

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Activity list

o Activity Attributes

o Milestone list

o Scope Baseline

o Actifs Organisationnels

PDM or AON ADM or AOA

GERT Méthode de détermination des dépendances Les Modèles

LEADS AND LAGS

The network diagram or the project schedule network diagram

project document updates (activity list; Activity Attributes ; Risk Register)

Page 10: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 10

PLANNING PROCESS GROUP (7/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

9 ESTIMATE ACTIVITY RESOURCES

TIME MANAGEMENT Activity Resource requirements

INPUTS TOOLS & TECHNIQUES OUTPUTS/IIVRABLES

o Activity list

o Activity Attribute list

o RESOURCE CALENDARS

o Actifs orgn

o Facteur Envi

Expert JudgmentJugement empirique

Analyse des possibilités

Données d’estimation publiées

BOTTOM-UP ESTIMATION (Estimation ascendante)

PM Software

Activity Resource requirements

RBS (structure de découpage des ressources)

Mises à jour des documents

Page 11: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 11

PLANNING PROCESS GROUP (8/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

10 ESTIMATE ACTIVITY DURATIONS

TIME MANAGEMENT Activity Duration Estimates

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Activity Resource requirementso Activity ListoAttribute Activity Listo RESOURCE CALENDARS

o Scope Statement

oActifs orgn

oFacteurs Envir

One-Point-EstimateAnalogous Estimating ou Top-Down Esimating Parametric Estimating (Scatter diagram or Learning Curve)Heuristics (s’appuie sur une règle de base/ rule of thumb)Three-Point Estimate (PERT) or EADANALYSE DE LA RESERVE

L’estimation de la Durée des Activités

Project Document Updates

Page 12: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 12

PLANNING PROCESS GROUP (9/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

11 DEVELOP SCHEDULE TIME MANAGEMENT Project Schedule

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Activity listoAttribute Activity Listo network diagramoActivity Resource RequirementsoActivity duration estimatesoProject scope statement

oRESOURCE CALENDARS

oActifs OrganisationnelsoFacteurs Envir

SCHEDULE NETWOK ANALYSIS

APPLYING LEADS AND LAGS

Project Schedule (sous +sieurs format : gantt chart or bar chart, milestone chart, etc.)

Schedule Baseline

Data schedule (données de base use lors de la mise en place du schedule)Project document updates

Page 13: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 13

PLANNING PROCESS GROUP (10/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

12 ESTIMATE ACTIVITY COSTS COST MANAGEMENT Activity Cost Estimate

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o The SCOPE BASELINE

oProject SCHEDULE

oHuman Resource Plan

oRisk Register

oActifs Organ

oFacteurs Environ

oProject Mgnt Cost

One-Point-EstimateAnalogous Estimating ou Top-Down Esimating Parametric EstimatingHeuristicsThree-Point Estimate Analyse de la ReserveBottom-Up EstimatingCOQ = Cost of QualityPM SoftwareVendor Bid analysisDetermining Resource Cost RateAccuracy of Estimates

Activity Cost Estimates

Basis of Estimates (Méthodes d’estimation)

Project Management Plan Updates

Project Document Updates

Page 14: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 14

PLANNING PROCESS GROUP (11/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

13 DETERMINE BUDGET COST MANAGEMENT Cost Baseline

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Activity cost Estimates

oBasis for Estimates

oScope BaseLine

oProject Schedule

oRESOURCE CALENDARS

oContracts

oActifs Organ

Cost Aggregation

Reserve Analysis

Expert Judgement

Historical Relationships or parametric estimating

Funding Limit Reconciliation

Cost Performance baseline

Project funding requirements

Project Document Updates

Page 15: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 15

PLANNING PROCESS GROUP (11/20) suite

Page 16: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 16

PLANNING PROCESS GROUP (12/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

14 PLAN QUALITY QUALITY Quality Management Plan

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Scope BaselineoStakeholder RegisteroCost Performance BaselineoSchedule BaselineoRisk RegisteroFacteurs EnviroActifs organisationnels

Cost-Benefit AnalysisCOQ : Cost of QualityControl ChartsBenchMarkingDOE : Design Of ExperimentStatistical SamplingFlowCharting (ex : Fishbone Diagram)Proprietary QM MethodologiesAdditional QM Tools

Quality Management Plan

Quality metrics

Quality Checklists

Process Improvement Plan

Projec Doc Updates

Page 17: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 17

PLANNING PROCESS GROUP (13/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

15 DEVELOP HR PLAN HR MANAGEMENT HR PLAN

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oActivity Resource Requirements

oFacteurs Envir

oActifs organisationnels

ORGANIZATION CHARTS AND POSITION DESCRIPTON

NETWORKING (MAILLAGE)

ORGANIZATIONAL THEORY

HR Plan (Roles and Responsabilities ; Organization charts ; Staffing Management Plan (recognition and rewards systems, etc…); Resource Histogram)

Page 18: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 18

PLANNING PROCESS GROUP (14/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

16 PLAN COMMUNICATIONS COMMUNICATION MANAGEMENT

COMMUNICATIONS MANAGEMENT PLAN

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oStakeholder Register

oStakeholder Management Strategy

oFacteur envir

oActifs organisationnels

Communication Requirements Analysis

Communication Channels

Communications Management Plan

Project Document Updates

Page 19: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 19

PLANNING PROCESS GROUP (15/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

17 PLAN RISK MANAGEMENT RISK MANAGEMENT Risk Mgnt Plan

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oPROJECT SCOPE STATEMENToCost Mgnt PlanoSchedule Mgnt Plan

oCOMMUNICATIONS MANAGEMENT PLAN

oFact EnviroActifs Organisationnels

PLANNING MEETINGS AND ANALYSIS RISK MANAGEMENT

PLAN (RBS, Methodology, Roles & Responsibility, Risk Categories, etc.)

Page 20: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 20

PLANNING PROCESS GROUP (16/20)

N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

18 IDENTIFY RISKS RISK MANAGEMENT RISK REGISTER

INPUTS TOOLS&TECHNIQUES OUTPUTS/LIVRABLES

oRisk Management PlanoActivity cost EstimatesoActivity duration EstimatesoScope BaselineoStakeholder RegisteroCost Management PlanoSchedule Mgnt PlanoQuality Mgnt PlanoProject Documents

oFacteurs EnviroActifs Organisationnels

Documentations ReviewsTechnique de Collecte d’InformationChecklist AnalysisAssumption Analysis (analyse des hypothèses)Diagramming Techniques (Ishikawa,flow charts)SWOT (Strengths, Weaknesses, Opportunities, Threats)

RISK REGISTER

Page 21: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 21

PLANNING PROCESS GROUP (17/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

19 PERFORM QUALITATIVE RISK ANALYSIS

RISK MANAGEMENT RISK REGISTER UPDATES

INPUTS TOOLS&TECHNIQUES OUTPUTS

oRisk Register

oRisk Management Plan

oProject Scope Statement

oActifs Organisationnels

Probability and Impact MatrixRisk probability and Impact Assessment

Risk Data Quality AssessmentRisk Categorization (RBS)

Risk Urgency Assessment

Expert Judgment

RISK REGISTER UPDATESA short List = risks to send in ‘Quantitative Risk analysis’

A Watch List = non-critical risks or non-stop risks (passeront directement à ‘Monitor and Control Risk’)

Page 22: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 22

PLANNING PROCESS GROUP (18/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

20 PERFORM QUANTITATIVE RISK ANALYSIS

RISK MANAGEMENT RISK REGISTER UPDATES

INPUTS TOOLS&TECHNIQUES OUTPUTS

oRisk Register

oRisk Management Plan

oCost Management Plan

oSchedule Management Plan

oActifs Organisationnels

DATA GATHERING AND REPRESENATION TECHNIQUES

PROBABILITY DISTRIBUTIONS

QUANTITATIVE RISK ANALYSIS AND MODELING TECHNIQUES

EXPERT JUDGMENT

RISK REGISTER UPDATES

Page 23: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 23

PLANNING PROCESS GROUP (19/20)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

21 PLAN RISK RESPONSES RISK MANAGEMENT RISK-RELATED CONTRACT DECISIONS

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oRisk Register

oRisk Managment Plan

STRATEGIES FOR NEGATIVE RISKS OR THREATS (Avoid, Transfert =Deflect or Allocate, Mitigate, Accept)

STRATEGIES FOR POSITIVE RISK OR OPPORTUNITIES (Exploit, Share, Enhance, Accept)

CONTINGENT RESPONSE STRATEGIES

Risk Register Updates

Project Mgnt plan UpdatesProject document UpdatesRisk-related Contract decisions

Page 24: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 24

PLANNING PROCESS GROUP (20/20)

N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

22 PLAN PROCUREMENTS PROCUREMENT MANAGEMENT

Procurement Mgnt PlanProcurement SOW

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oScope BaselineoRequirements DocumentationoTeaming Agreements (Accords de Partenariat)oRisk RegisteroRisk-related contract decisionoActivity Resource Requirements oProject ScheduleoActivity Cost EstimatesoCost Performance BaselineoFact Envir + Actifs Org.

Make-or-Buy Analysis

Expert Judgment

Contract Types:-FP-CR-T&M

Procurement Management Plan

Procurement SOW (Performance, Functional, Design)

Change Requests

Make-or-Buy Decisions

Page 25: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 25

EXECUTING PROCESS GROUP (1/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

23 DIRECT & MANAGE PROJECT EXECUTION

INTEGRATION Les Livrables

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o Project plan

o Appoved Change Requests

o Actifs Org

o Facteurs Envir

EXPERT JUDGMENT

PMIS (Project Management Information System)

Les livrables Work Performance Information

Change Requests

Project Management Plan UpdatesProject Document Updates

Page 26: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 26

EXECUTINGDE PROCESS GROUP (2/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

24 ACQUIRE PROJECT TEAM « Acquire final project team »

HR MANAGEMENT -Project Staff Assignments- Resource calendars

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o LE PLAN PROJET (HR plan)

o Actifs org

o Facteurs Envir

PRE-ASSIGMENT (pré-affectation)

NEGOCIATION (int/ext)

ACQUISITION (chercher à l’extérieur si on n’a personne en interne)

VIRTUAL TEAM

PROJECT STAFF ASSIGNMENTS

Calendriers de Ressource / RESOURCE CALENDARS

Project Management Plan Updates

Page 27: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 27

EXECUTING PROCESS GROUP (3/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

25 DEVELOP PROJECT TEAM HR MANAGEMENT Team Performance assessment

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o PROJECT STAFF ASSIGNMENTS

o PLAN PROJET (HR PLAN)

o RESOURCE CALENDARS

INTERPERSONAL SKILLS or SOFT SKILLS TRAINING TEAM-BUILDING ACTIVITIES GROUND RULES CO-LOCATION / WAR ROOM RECOGNITION AND REWARDS (or thories of motivation)

Team Performance Assessment

Enterprise Envioronmental Factors Updates

Page 28: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 28

EXECUTING PROCESS GROUP (4/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

26 MANAGE PROJECT TEAM HR MANAGEMENT CHANGE REQUESTS

INPUTS TOOLS&TECHNIQUES OUTPUTS/LIVRABLES

oProject Staff Assignments

oProject Mgnt Plan

oTeam Performance Assessments

oPERFORMANCE REPORTS

oActifs Organisationnels

OBSERVATION AND CONVERSATION

PROJECT PERFORMANCE APPRAISALS (360°Review)

CONFLICT MANAGEMENT

ISSUE LOGS

INTERPERSONAL SKILLS

change Requests

Mises à jour des Actifs Organisationnels

Mises à jour Facteurs Environnementaux

Project Plan Updates

Page 29: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 29

EXECUTING PROCESS GROUP (5/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

27 PERFORM QUALITY ASSURANCE

QUALITY MANAGEMENT

CHANGE REQUESTS

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oProject Management Plan

oMétrics Qualité

oWork Performance Information

oQuality Control Measurements

Tools & Techniques of Plan Quality and Perform Quality control +

QUALITY AUDIT

PROCESS ANALYSIS.

Change Requests (Recommend Corrective and preventive actions; defect repair)

Updated Standards and processes

Updated PM plan and project documents

Page 30: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 30

EXECUTING PROCESS GROUP (6/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

28 DISTRIBUTE INFORMATION COMMUNICATIONS MANAGEMENT

MISES A JOUR DES ACTIFS ORGANI.

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oProject Management Plan (Communications Mgnt Plan)

oPERFORMANCE REPORTS

oActifs Organisationnels

Communications Methods

Information Distribution Tools

Mises à jour des Actifs Organisationnels

Page 31: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 31

EXECUTING PROCESS GROUP (7/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

29 MANAGE STAKEHOLDER EXPECTATIONS

COMMUNICATIONS MANAGEMENT

Change Requests

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oStakeholder RegisteroLa strategie de management des parties prenantes

oProject Plan (to exploit Communications Management Plan)

oIssue LogoChange Log

oActifs Organisationnels

Communication Methods

Soft-Skills or Interpersonal Skills

Management Skills

(‘mener à bien les demandes des stakeholders)Updates des Actifs organisationnels

Change Requests

Updates du Plan ProjetUpdates des Docs Projet (Lessons Learned; stakeholder management strategy; stakeholder register; etc.)

Page 32: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 32

EXECUTING PROCESS GROUP (8/8)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

30 CONDUCT PROCUREMENTS PROCUREMENTS MANAGEMENT

-Select Sellers;- procurement Conctract award

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oLe plan ProjetoProcurement DocumentsoCritère de Sélection des SourcesoListe des Sellers QualifiésoSeller ProposalsoProject DocumentsoMake-or-Buy DecisionsoTeaming Agreements

oActifs Organisationnels

Bidder Conference

Proposal Evaluation TechniquesEstimations IndépendantesExpert JudgmentPublicitéRecherches sur InternetProcurement Negociations

Vendeurs SélectionnésAttribution des Contrats d’approv.

Resource CalendarsChange Requests

Project Mgnt Plan UpdatesProjet Documents Updates

Page 33: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 33

M&C PROCESS GROUP (1/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

31 MONITOR AND CONTROL PROJECT WORK

INTEGRATION MANAGEMENT

Change Requests

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o The project plano Performance Reporto Facteurs Enviro Actifs Organisationnels

Expert Judgment Change Requests

Project Plan Updates

Project Documents Updates

Page 34: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 34

M&C PROCESS GROUP (2/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

32 PERFORM INTEGRATED CHANGE CONTROL

INTEGRATION MANAGEMENT

Change Requests Status Updates

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oProject Mgnt Plan

oWORK PERFORMANCE INFORMATION

oChange Requests

oFacteurs Envir

oActifs Org

Expert Judgment

Change Control Meetings

Change Requests Status Updates

Project Mgnt Plan Updates

Project Documents Updates

Page 35: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 35

M&C PROCESS GROUP (3/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

33 CONTROL SCOPE SCOPE MANAGEMENT WORK PERFORMANCE MEASUREMENTS

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oLe plan Projet

oWORK PERFORMANCE INFORMAITON

oRequirements Documentation

oMatrice de Traçàbilité des Exigences

oActifs Orgn.

VARIANCE ANALYSIS WORK PERFORMANCE MEASUREMENTS

CHANGE REQUESTS

MISES A JOUR DES ACTIFS ORGAN.

MISES A JOUR DU PLAN PROJET

MISES A JOUR DES DOC PROJET

Page 36: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 36

M&C PROCESS GROUP (4/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

34 VERIFY SCOPE SCOPE MANAGEMENT Accepted Deliverables

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

o VALIDATED DELIVERABLES(output du processus : Perform Quality Control

o Requirements documentation

oMatrice de traçabilité des exigences

INSPECTION ACCEPTED DELIVERABLES(livrables acceptés)

Change Requests

Project Document Updates

Page 37: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 37

M&C PROCESS GROUP (5/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

35 CONTROL SCHEDULE TIME MANAGEMENT Work Performance Measurements

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oThe Project Schedule

oThe Project Plan (contient « project schedule management » and schedule baseline)

oWORK PERFORMANCE INFORMATION

oActifs Organisationnels

PERFORMANCE REVIEWVARIANCE ANALYSISProject Management SoftwareResource LevelingWhat-if-Scenario AnalysisAdjusting Lags and LeadsSchedule compressionScheduling Tool

WORK PERFORMANCE MEASUREMENTS (SPI, SV, etc.)CHANGE REQUESTS

Mises à jour des Actifs organisationnelsMises à jour du Plan ProjetProject Document Updates

Page 38: PMP Exam - The 42 pmp-processes - 4th Edition

38

M&C PROCESS GROUP (6/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

36 CONTROL COSTS TIME MANAGEMENT Work Performance Measurements

INPUTS TOOLS&TECHNIQUES OUTPUTS/LIVRABLES

o Plan projet (mostly « Cost Performance Baseline » + « Cost Mgnt Plan »)

oProject Funding Requirements

oWork Performance Information

oOrganization process Assets

Earned Value Measurement

Forecasting

Performance Reviews

Variance Analysis

PM Software

Work Performance Measurements (CV, SV, CPI, SPI, CPIC, etc.)Budget Forecasts (EAC, ETC, etc.)Mises à Jour des Actifs OrganisationnelsChange RequestsMises à Jour du Plan ProjetProject Document Updates

By ElyMad © 2011

Page 39: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 39

M&C PROCESS GROUP (7/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

37 PERFORM QUALITY CONTROL

QUALITY MANAGEMENT -Quality Control Measurements-Validated Deliverables

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oPlan ProjetoMétriques QualitéoQuality checklist (liste de contrôle qualité)oWORK PERFORMANCE MEASUREMENTS (Mesures de performance du travail)oApproved Change RequestsoActifs OrganisationnelsoLivrables

Ishikawa or FishboneControl chartFlowchartingHistogramPareto chart (histogram particulier)Run ChartScatter ChartStatistical SamplingInspectionApproved Change Requests Review

QC MEASUREMENTSUpdates to the project management plan and project documentChange Requests (recommended corrective and preventive actions; and defect repair)Lesson learnedValidated changesValidated Deliverables. (input of ‘Verify Scope’)

Page 40: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 40

M&C PROCESS GROUP (8/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

38 REPORT PERFORMANCE COMMUNICATIONS MANAGEMENT

PERFORMANCE REPORTS

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oLe Plan Projet (to exploit the diff baseline)

oWORK PERFORMANCE INFORMATION

oWORK PERFORMANCE MEASUREMENTS

oBUDGET FORECASTS

oACTIFS ORGANISAT.

Variance Analysis (Analyse de l’écart)

Forecasting Methods(Méthodes de Prévision : EAC, ETC)

Communications Methods

Reporting Systems (Système de Rapports)

Performance Reports (Input de ‘Distribute Information’)

Change Requests

Mises à jour des Actifs Organisationnels.

Page 41: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 41

M&C PROCESS GROUP (9/10)

N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

39 MONITOR AND CONTROL RISKS

RISKS MANAGEMENT -Risk Register Updates-Change Requests

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oRISK REGISTER

oPROJECT MANAGEMENT PLAN

oWORK PERFORMANCE INFORMATION

oPERFORMANCE REPORTS

Risk Reassessment Risk Audits

Variance and Trend AnalysisTechnical Performance Measurements

Reserve AnalysisStatus Meetings

Risk Register Updates

Mise à jour des Actifs Organisationnels

CHANGE REQUESTS

Project Management UpdatesProject Document Updates

Page 42: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 42

M&C PROCESS GROUP (10/10)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

40 ADMINISTER PROCUREMENTS

PROCUREMENTS MANAGEMENT

CHANGE REQUESTSPROC DOCUMENTATION

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oProcurement DocumentsoProject Plan

oCONTRACToPERFORMANCE REPORTS (Rapports d’Avancement)

oAPPROVED CHANGE REQUESTS

oWORK PERFORMANCE INFORMATION (Infos sur la perf du travail)

CONTRACT CHANGE CONTROL SYSTEMProcurement Performance ReviewsINSPECTIONS & AUDITSPerformance ReportingPayment SystemsClaims Administration (Gesiton des Reclammations)Système de Mgnt des Enregistrements (Records Mgnt System)

CHANGE REQUESTS

PROCUREMENT DOCUMENTATION

MISES A JOUR DES ACTIFS ORGAN.

MISES A JOUR DU PLAN PROJET

Page 43: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 43

CLOSING PROCESS GROUP (1/2)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

41 CLOSE PROJECT OR PHASE INTEGRATION MANAGEMENT

Final Product, Service or Result Transition

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oLE PLAN PROJET

oACCEPTED DELIVERABLES

oACTIFS ORGANISATIONNELS

EXPERT JUDGMENT FINAL PRODUCT, SERVICE OR RESULT TRANSITION

MISES A JOUR DES ACTIFS ORGANISATIONNELS

Page 44: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 44

CLOSING PROCESS GROUP (2/2)N° PROCESS NAME KNOWLEDGE AREA MAIN OUTPUT

42 CLOSE PROCUREMENTS PROCUREMENTS MANAGEMENT

Close Procurements

INPUTS TOOLS&TECHNIQUES OUTPUTS/IIVRABLES

oPROJECT MANAGEMENT PLAN

oPROCUREMENT DOCUMENTATION

PROCUREMENT AUDITS

NEGOTIATED SETTLEMENTS (Règlement négociés)

RECORDS MANAGEMENT SYSTEM

CLOSED PROCUREMENTS

MISES A JOUR DES ACTIFS ORGAN.

Page 45: PMP Exam - The 42 pmp-processes - 4th Edition

By ElyMad © 2011 45

Bibliographie• PMP Exam Prep, sixth edition (align with the PMBok Guide © fourth

edition , RITA Mulcahy, PMP (World Renowned PMP Author, trainer and speaker. 2009

• Project Management Body of Knowledge (PMBOK® GUIDE), fourth edition, PMI 2008

• Project Managmenet Professional Exam, STUDY GUIDE, fourth edition, Kim HELDMAN, 2007

• Andy Crowe,